Southern California Edison TLRR - 500 kV

South Central California, USA

South Central California, USA - April 2017

Two Single Circuit 500 kV towers were raised 10ft & 15ft. The project was completed in 10 days.  

This raise project had many interesting challenges. The first structure was located within the beautiful Tejon Ranch, a highly environmentally sensitive privately held parcel of land, within the state of California. The 2nd tower raise was at a railroad crossing located in a well-established neighborhood.

The AMPJACK® Tower Raising technique helped reduce other environmental impact concerns such as nesting birds and burrowing animals.