Southern California Edison 220kV TLRR

South Central California, USA May 2017

Four Double Circuit 220kV towers were raised 10ft and 15ft, while the transmission line remained energized.  The project was completed in a total of 12 days.  

The towers were located in varied terrain, including densely populated residential area, environmentally sensitive high desert plains, among the Joshua tree growths, and on Federal Bureau of Land Management territory. 

Within the BLM territory, all equipment was placed at the tower site without any rubber tire vehicles leaving the access trail. 

AMPJACK® offered an extremely light footprint, which allowed fast tracking of the environmental permitting required for this transmission line upgrade project.